Hi,
The tiles in my new build don’t line up from about half way up they stop lining up as he measured the wall wrong and did a full tile at the bottom. This has meant when he hit the niche it has not been factored in properly and they stop lining up from that point.

He still has a ton of work to do (probably 4 days worth) and is going to another job and I have no idea when he’ll be back (they have to grind down concrete as they forgot to put a fall in the alfresco- another error)

I was due to pay cash for a couple toilets that he completed (organised separately) do I pay? Or do I use that as leverage for fixing the rest of the job? How should I handle this? Any advice

Comments (2)