Building Jargon Untangled for the Average Homeowner
These jargon busters will give you more confidence during the building process, and could potentially save you thousands
Adam Hobill
1 April 2015
Read more about conquering the building process in my new book, 'Nail it! Take control of your building project & save thousands'. When I decided to write the book I set out with a simple goal; to educate and empower homeowners to help them complete a building project with less stress and with less risk of budget blow outs. It's all about getting homeowners on a level playing field with their builder.
Read more about conquering the building process in my new book, 'Nail it! Take control... More
Building is like any other industry; there’s a lot of terminology used and it’s easy to feel lost and anxious about what you are embarking on. Here are some terms that are often misunderstood (even within the industry at times), but will become very important once they appear in building contracts awaiting your signature. Understanding the proper use of these terms will put you on a level playing field with builders when you start to consider quotes and sign contracts, helping you to reduce stress and eliminate budget blow-outs.
What’s the most annoying piece of building jargon?
What’s the most annoying piece of building jargon?
‘Prime cost’
The term ‘prime cost’ (PC) is used a lot in the quoting and contractual stages of building. Prime costs are dollar allowances that are made for the supply of items where the final selection is yet to be confirmed. Common examples include appliances, taps, sinks and tiles. A prime cost allowance is for the cost of the item only, so the builder needs to allow for the installation of the item separately. Importantly, because a prime cost is an allowance only, it is subject to change depending on the final selection of the item. So if you select an item that costs more than the prime cost allowance, you will need to pay the difference as an extra.
PRO TIP: Ensure the prime cost allowances in quotes are realistic in terms of the quality you expect (I use the ProSpex Inclusions Specification tool on buildingquote).
The term ‘prime cost’ (PC) is used a lot in the quoting and contractual stages of building. Prime costs are dollar allowances that are made for the supply of items where the final selection is yet to be confirmed. Common examples include appliances, taps, sinks and tiles. A prime cost allowance is for the cost of the item only, so the builder needs to allow for the installation of the item separately. Importantly, because a prime cost is an allowance only, it is subject to change depending on the final selection of the item. So if you select an item that costs more than the prime cost allowance, you will need to pay the difference as an extra.
PRO TIP: Ensure the prime cost allowances in quotes are realistic in terms of the quality you expect (I use the ProSpex Inclusions Specification tool on buildingquote).
‘Provisional sum’
‘Provisional sums’ (PS) are similar to prime costs in that they are also allowances that are made for tasks where the final selection is not yet confirmed or where there is detail lacking at the time of quoting. The big (and important) difference however is that provisional sums are an allowance for both materials and labour to complete the task. Examples of areas where provisional sums get used include retaining walls, structural steel and other detailed elements of a building.
Just like prime costs, provisional sums are allowances only and are therefore also subject to change depending on the final cost of completing the required task. Because you will have less control over the actual costs of provisional sum expenses, the key tip here is to eliminate as many provisional sums from your quote as possible by having them included as fixed items. If your drawings are sufficiently detailed there should be little need for provisional sums in your quote as builders will be able to quote what is required without needing to rely on provisional sums.
‘Provisional sums’ (PS) are similar to prime costs in that they are also allowances that are made for tasks where the final selection is not yet confirmed or where there is detail lacking at the time of quoting. The big (and important) difference however is that provisional sums are an allowance for both materials and labour to complete the task. Examples of areas where provisional sums get used include retaining walls, structural steel and other detailed elements of a building.
Just like prime costs, provisional sums are allowances only and are therefore also subject to change depending on the final cost of completing the required task. Because you will have less control over the actual costs of provisional sum expenses, the key tip here is to eliminate as many provisional sums from your quote as possible by having them included as fixed items. If your drawings are sufficiently detailed there should be little need for provisional sums in your quote as builders will be able to quote what is required without needing to rely on provisional sums.
However, keep in mind that seeing a couple of provisional sums in your quotes is not such a bad thing if they are informed estimates rather than guesses; but if you see lots of provisional sums in your quote it may be a sign of lazy quoting.
Unfortunately, the use of provisional sums is an area where some builders take advantage of clients. By including unnecessary and unrealistically low provisional sum allowances in their quote, builders are able to make the quote appear more competitive while at the same time also shift the risk to the client, knowing that any shortfall in the final costs will be passed directly onto the client. This strategy is supported by the ability for builders to then also charge the client a ‘builder’s margin’ on top of the difference between their allowance and the actual cost of completing the nominated task.
Unfortunately, the use of provisional sums is an area where some builders take advantage of clients. By including unnecessary and unrealistically low provisional sum allowances in their quote, builders are able to make the quote appear more competitive while at the same time also shift the risk to the client, knowing that any shortfall in the final costs will be passed directly onto the client. This strategy is supported by the ability for builders to then also charge the client a ‘builder’s margin’ on top of the difference between their allowance and the actual cost of completing the nominated task.
‘Builder’s margin’
The most commonly used building contracts in Australia are the HIA & MBA contracts, both of which make provision for builders to charge a margin of up to 20 per cent for ‘variations’ (or changes) to the contract in addition to the cost of the difference in what was allowed as a provisional sum and the final cost of that item. For example, the builder includes a provisional sum for the installation of feature cladding of $5,000 in their quote. The final cost of supplying and installing the cladding (remembering that the PS includes supply and labour) ends up being $7,700; which is $2,700 more than what was allowed.
Speak to a cladding contractor for advice on what will work best for you
The most commonly used building contracts in Australia are the HIA & MBA contracts, both of which make provision for builders to charge a margin of up to 20 per cent for ‘variations’ (or changes) to the contract in addition to the cost of the difference in what was allowed as a provisional sum and the final cost of that item. For example, the builder includes a provisional sum for the installation of feature cladding of $5,000 in their quote. The final cost of supplying and installing the cladding (remembering that the PS includes supply and labour) ends up being $7,700; which is $2,700 more than what was allowed.
Speak to a cladding contractor for advice on what will work best for you
The client will need to pay the $2,700 difference, and because the cladding was nominated as a provisional sum, the builder may also charge the client with a builder’s margin of $540 (20 per cent of $2,700), bringing the total cost of the variation up to $3,310. This highlights the need to be wary of how provisional sums are used in quotes. If they really must be in there – which is the case for some items – you should be confident that the builder has invested some time into working out a realistic allowance rather than simply guessing an allowance.
‘Variations’
‘Variations’ are simply additional costs on top of the contract (quoted) price, and they may take the form of materials and/or labour costs. Under the provisions of most building contracts, a variation occurs when work outside the scope of the original contract is introduced, or when items within the contract are adjusted, which includes our friend’s prime costs and provisional sums. Generally speaking, if the cost of a variation is a result of the client changing their mind or altering the scope of work, the client will be exposed to being charged a variation and a builder’s margin of up to 20 per cent.
Like this kitchen? See more beautiful designs here.
‘Variations’ are simply additional costs on top of the contract (quoted) price, and they may take the form of materials and/or labour costs. Under the provisions of most building contracts, a variation occurs when work outside the scope of the original contract is introduced, or when items within the contract are adjusted, which includes our friend’s prime costs and provisional sums. Generally speaking, if the cost of a variation is a result of the client changing their mind or altering the scope of work, the client will be exposed to being charged a variation and a builder’s margin of up to 20 per cent.
Like this kitchen? See more beautiful designs here.
If the variation is due to a miscalculation or mistake from the builder, then the builder will be responsible for the variation and will need to absorb the costs. In the case of unforeseen costs that cannot reasonably be accounted for at the time of quoting (more likely with extensions and renovations than new builds), the client will generally need to pay the variation.
Here are six key examples of how variations may be applied:
1. If the builder has miscalculated the number of roof tiles required to complete the new roof of an extension and needs an additional 220 tiles, the builder will be responsible for the additional costs and a variation and margin cannot be charged to the client, as the drawings and scope of work have not changed. The additional cost must be absorbed by the builder as it was his error in quoting.
2. If you ask the builder to install terracotta roof tiles for an extension instead of the concrete roof tiles shown on the drawings, a variation and margin can be charged for the difference in the cost of roof tiles, as the drawings stated concrete tiles and they were what the builder quoted.
1. If the builder has miscalculated the number of roof tiles required to complete the new roof of an extension and needs an additional 220 tiles, the builder will be responsible for the additional costs and a variation and margin cannot be charged to the client, as the drawings and scope of work have not changed. The additional cost must be absorbed by the builder as it was his error in quoting.
2. If you ask the builder to install terracotta roof tiles for an extension instead of the concrete roof tiles shown on the drawings, a variation and margin can be charged for the difference in the cost of roof tiles, as the drawings stated concrete tiles and they were what the builder quoted.
3. If you request two garden taps to be installed on the external walls, a variation and margin can be charged if the taps were not indicated on the drawings. However, a variation and margin cannot be charged if these taps were included as required in an inclusions schedule.
4. If the electrician finds that, upon commencing a renovation project and exposing the electrical wiring, it does not comply with current standards, he is bound by law to replace and upgrade the wiring throughout the house. In this case, a variation and margin can be charged as the requirement to replace the wiring was not known at the time of quoting and no allowance was made in the quote for such work.
4. If the electrician finds that, upon commencing a renovation project and exposing the electrical wiring, it does not comply with current standards, he is bound by law to replace and upgrade the wiring throughout the house. In this case, a variation and margin can be charged as the requirement to replace the wiring was not known at the time of quoting and no allowance was made in the quote for such work.
5. If the bricklayer has increased his laying rate and the builder wishes to pass that additional cost on to the client, a variation and margin cannot be charged, as the quote included the laying of bricks as shown in the drawings.
6. If the electrician has increased his cost to install each light point by 10 per cent and the builder wishes to pass on this cost increase, a variation and margin can be charged if the builder has noted a cost per light point as a provisional sum in the quote. However, a variation and margin cannot be charged if the cost per point is not nominated as a provisional sum in the quote.
You can see the important role that understanding industry terminology has in ensuring high-quality and sufficiently detailed documentation, ensuring you and your builder are on the same page. Thoroughness and transparency is critical.
6. If the electrician has increased his cost to install each light point by 10 per cent and the builder wishes to pass on this cost increase, a variation and margin can be charged if the builder has noted a cost per light point as a provisional sum in the quote. However, a variation and margin cannot be charged if the cost per point is not nominated as a provisional sum in the quote.
You can see the important role that understanding industry terminology has in ensuring high-quality and sufficiently detailed documentation, ensuring you and your builder are on the same page. Thoroughness and transparency is critical.
‘Fixed price’
Builders will sometimes use the enticement of a ‘fixed price contract’ to attract potential clients. The idea of a fixed price contract is a wonderful thing, however it is very rare that any building contract will truly be fixed price because prime cost and provisional sum allowances are written into most contracts. As mentioned above, the more provisional sums in the contract, the more exposed you are to cost variations and budget blow-outs, even when signing a fixed price contract.
Builders will sometimes use the enticement of a ‘fixed price contract’ to attract potential clients. The idea of a fixed price contract is a wonderful thing, however it is very rare that any building contract will truly be fixed price because prime cost and provisional sum allowances are written into most contracts. As mentioned above, the more provisional sums in the contract, the more exposed you are to cost variations and budget blow-outs, even when signing a fixed price contract.
When a builder includes a task in his quote (i.e. not nominating the task as a provisional sum), he is taking responsibility for the cost and accepting the risk of a change in cost; so he is more likely to have quoted it accurately and to be diligent about completing the task cost effectively.
By contrast, when a builder includes a task as a provisional sum, he is dissolving his responsibility and shifting the risk to you if there is any increase in the actual cost of that task. Because he doesn’t bare any of the additional costs, he may also be less diligent about controlling the cost to complete the task.
Ultimately, you should try to limit the number of provisional sums in the quote. As you negotiate with builders, you may need to ask them to reconsider some of the provisional sums and have them included in the quote as part of the fixed price.
By contrast, when a builder includes a task as a provisional sum, he is dissolving his responsibility and shifting the risk to you if there is any increase in the actual cost of that task. Because he doesn’t bare any of the additional costs, he may also be less diligent about controlling the cost to complete the task.
Ultimately, you should try to limit the number of provisional sums in the quote. As you negotiate with builders, you may need to ask them to reconsider some of the provisional sums and have them included in the quote as part of the fixed price.
Find out more about Adam’s new book, Nail It!: Take Control of Your Building Project and Save Thousands on his Houzz profile.
TELL US
What piece of building industry jargon has you in a tangle?
MORE TIPS
5 Industry Tips for Cost-Effective Building and Renovating
The (Sustainable) Case for Renovating Instead of Building
How to Get On With Your Neighbours During a Reno
TELL US
What piece of building industry jargon has you in a tangle?
MORE TIPS
5 Industry Tips for Cost-Effective Building and Renovating
The (Sustainable) Case for Renovating Instead of Building
How to Get On With Your Neighbours During a Reno
Related Stories
Architecture
9 Things You Need to Know Before Hiring an Architect
Go on a fact-finding mission before settling on an architect to clarify fees and exactly what you'll get for your money
Full Story
Lifestyle
From the Pros: A Practical Guide to Feng Shui
A harmonious home filled with positive energy starts with a few thoughtful adjustments – and a little expert know-how
Full Story
Decorating
The Case for Hiring a Home Stager
To help you sell your home, and potentially achieve a higher sale price, consider hiring a professional stager to style it for you
Full Story
Renovating
A Beginner’s Guide to Managing an Interior Design Project
Want to learn how to manage your own home renovation project? Read through these expert tips and you'll be a pro in no time
Full Story
Renovating
A Crash Course in Learning to Speak Builderese
By Alix Davis
Learn some common building terms to make communicating with your builder throughout a renovation project that little bit easier
Full Story
Colour
Does Your Home Need a Colour Consultant?
By Janet Dunn
Engaging a colour consultant could be one of the smartest moves you make, to help your home to look its best
Full Story
Lifestyle
Behind the Lens: Houzz Photographers Share Their Favourite Shots
Our photographers take you out on the job and reveal their tips and tricks on how to get that perfect pic
Full Story
Renovating
10 Questions to Ask Yourself Before You Plan an Extension
By Adam Hobill
Need more space? Here are a few things to think about if extending is on your mind
Full Story
Renovating
Is Your Builder Giving it to You Straight?
By Adam Hobill
Knowing what advice to take and what to cast aside is half the battle of a building project, especially for first timers
Full Story
Renovating
5 Signs That You Need an Interior Designer
By Nelly Reffet
As design-savvy as we are, we all need help sometimes. Let's explore some situations where we can benefit from calling in the experts
Full Story
After reading this I feel well prepared for a meeting with my builder this week. I won't need to worry when I hear the terms 'prime cost' or 'provisional sum'. I always thought a fixed contract would protect us so I'm pleased to be informed about other common terms.
Thanks!
We are also meeting with the builder next week, I'm stoked to now understand the difference between prime cost and provisional sums. Thanks!